Friday, November 12, 2010

TRANSFER CONSTITUTES INDUSTRIAL DISPUTE

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

DATED: 01/11/2010

CORAM

THE HONOURABLE MR.JUSTICE K.CHANDRU

W.P.(MD)NO.7109 of 2009

and

W.P.(MD)NO.9607 and 9608 of 2010

and

M.P.(MD)No.1 of 2009 and 1 and 1 of 2010

Cement and Quarry Workers Union,

represented by its General Secretary

A.Vailkandan,

173F, Madurai Road,

Sankar Nagar,

Tirunelveli District. .. Petitioner in

all writ petitions

vs

1.The Secretary to Government,

Ministry of Labour,

Government of India,

New Delhi.

2.The Assistant Commissioner of Labour (Central),

Lady Doak College Road,

Chinna Chokkikulam,

Madurai-625 002.

3.The Management,

The India Cements Ltd.,

Sankar Nagar,

Tirunelveli District. .. Respondents in

all writ petitions

W.P.(MD)No.7109 of 2009 has been preferred under Article 226 of the Constitution

of India praying for the issue of a writ of certiorarified mandamus to call for

the records relating to the impugned order passed by the first respondent dated

30.01.2009, to quash the same and consequently, to direct the first respondent

to refer the matter to the labour court for adjudication as contemplated under

Industrial Disputes Act, 1947.

W.P.(MD)Nos.9607 and 9608 of 2010 have been preferred under Article 226 of the

Constitution of India praying for the issue of a writ of certiorarified mandamus

to call for the records relating to the impugned orders in No.L-29011/19/2009-

IR(M), L-29011/17/2009-IR(M) passed by the first respondent dated 9.3.2010 and

15.2.2010, to quash the same and consequently, to direct the first respondent to

refer the matter to the labour court for adjudication as contemplated under

Industrial Disputes Act, 1947.

!For Petitioner ... Mr.L.Shaji Chellan in WP(MD).7109 of 2009

Mr.S.M.Mohan Gandhi

in WP(MD)Nos.9607 and 9608 of 2010

^For Respondents ... Mr.S.Sukumaran, Senior Panel counsel

for RR1 and 2 in W.P.(MD)No.7109 of 2009

Mr.S.Jayaraman, SC for Mr.A.Veerasamy for R-3

in all writ petitions

Mr.K.K.Senthilvelan for RR1 and 2

in WP(MD)Nos.9607 and 9608 of 2010

- - - -

:COMMON ORDER

All the three writ petitions were filed by the petitioner union, seeking

to challenge the orders of the first respondent, dated 30.01.2009, 09.03.2010

and 15.2.2010.

2.In W.P.(MD)No.7109 of 2009, the petitioner union raised a dispute

against the transfer of one R.Rengasamy from Sankar Nagar at Tirunelveli to

Raasi Works in Andhra Pradesh before the Central Labour Commissioner. The

Conciliation Officer, i.e. Assistant Labour Commissioner (Central), Madurai sent

a failure report, dated 29.8.2008 to the Central Government. The Central

Government upon receipt of the said report, by an order, dated 30.1.2009,

declined to refer the dispute and gave the following reasons:

"Having accepted the terms and conditions of the appointment order, the Union

cannot take a plea of transfer as an unfair labour practice at this point of

time. Moreover, transfer is a prerogative of the management."

It is this order which is under challenge in this writ petition.

3.On notice from this court, the third respondent India Cements Ltd. has

filed a counter affidavit, dated 18.10.2010 together with supporting documents.

The principal contention raised by the management was that transfer was made on

31.1.2005. The petitioner had joined in the Raasi Works, Andhra Pradesh on

21.2.2005. Therefore, they are guilty of delay. Further, the terms of

appointment given to the petitioner shows that he can be transferred to any

other unit such as Factory, Mines, Head Office, Foundry Division, Chilamkur

(Factory/Mines), Sankari (Factory/Mines), Factory and Mines formed and acquired

by the same management. Therefore, there was no scope for adjudicating such

dispute. The first and second respondents have also filed a counter affidavit,

dated 08.04.2010.

4.Per Contra, Mr.L.Shajji Chellan, learned counsel for the petitioner

stated that the Standing Order applicable to the factory only provides for

transfer of workers from one shift to another shift in the interest of the

Company. There is no scope for transferring the workers from one factory to

another factory and that too the factory which was established long after the

petitioner joined the service and also to the far off place in an another State,

i.e. Andhra Pradesh.

5.In W.P.(MD)No.9607 of 2010, the petitioner union raised a dispute

relating to transfer of one Kulandai Jesu from Sankar Nagar, Tirunelveli to

Bhimavaram in Andhra Pradesh. The dispute was conciliated by the Assistant

Labour Commissioner, Madurai. As he could not bring about mediation, he sent a

failure report to the Government of India, dated 24.9.2009. The Government of

India upon receipt of the same, by the impugned order, dated 9.3.2010 declined

to refer the dispute and passed an order that "Transfer is a prerogative of the

management."

It is this order which is under challenge in this writ petition. The third

respondent has filed a counter affidavit, dated 18.10.2010 and had raised

similar contentions as in the case of workmen Rengasamy.

6.In W.P.(MD)No.9608 of 2010, the petitioner union raised a dispute

regarding transfer of its member N.Krishnan from Sankar Nagar, Tirunelveli to

Sankari Works, Salem. The dispute was conciliated by the Assistant Labour

Commissioner (Central), Madurai. As he could not bring about mediation, he sent

a failure report, dated 31.8.2009 to the Government of India. The Government of

India, by its order, dated 15.2.2010, exercising power under Section 10(1) of

the Industrial Disputes Act, declined to refer the dispute and gave the

following reasons:

"Transfer of workman is prerogative of the management and cannot constitute an

industrial dispute."

The petitioner Union has challenged the same in this writ petition. On notice

from this court, the third respondent management had raised identical

contentions in its counter affidavit, dated 18.10.2010 in this writ petition

also.

7.In view of the commonality among the three writ petitions, they were

grouped together and a common order is passed.

8.Heard the arguments of Mr.L.Shaji Chellan and Mr.S.M.Mohan Gandhi,

learned counsel appearing for petitioners and Mr.S.Sukumaran,

Mr.K.K.Senthilvelan and Mr.S.Jayaraman, learned Senior Counsel for

Mr.A.Veerasamy, learned counsel appearing for respondents.

9.The three orders of the Central Government referred to prerogative power

of the employer to transfer the employees. The learned senior counsel for the

third respondent Mr.S.Jayaraman contended that the orders should not be

interfered with on the ground of delay in approaching the court. The employer

had incorporated the said clause in the orders of appointment issued to the

petitioners. In a writ in the nature of certiorari, one cannot supply reasons

which are not found on the face of the order.

10.Even otherwise, the Supreme Court on the question of delay in raising

the dispute dealt with several judgments and has held that the delay cannot be

the sole reason for denying the relief. In this context, it is necessary to

refer to the judgment of the Supreme Court in Karan Singh v. Haryana State

Marketing Board reported in (2007) 14 SCC 291. The following passage found in

paragraph 15 from the said judgment may be usefully extracted below:

15. "10. So far as delay in seeking the reference is concerned, no formula of

universal application can be laid down. It would depend on the facts of each

individual case.

11. However, certain observations made by this Court need to be noted. In

Nedungadi Bank Ltd. v. K.P. Madhavankutty4 it was noted at para 6 as follows:

(SCC pp.459-60)

'6. Law does not prescribe any time-limit for the appropriate Government to

exercise its powers under Section 10 of the Act. It is not that this power can

be exercised at any point of time and to revive matters which had since been

settled. Power is to be exercised reasonably and in a rational manner. There

appears to us to be no rational basis on which the Central Government has

exercised powers in this case after a lapse of about seven years of the order

dismissing the respondent from service. At the time reference was made no

industrial dispute existed or could be even said to have been apprehended. A

dispute which is stale could not be the subject-matter of reference under

Section 10 of the Act. As to when a dispute can be said to be stale would depend

on the facts and circumstances of each case. When the matter has become final,

it appears to us to be rather incongruous that the reference be made under

Section 10 of the Act in the circumstances like the present one. In fact it

could be said that there was no dispute pending at the time when the reference

in question was made. The only ground advanced by the respondent was that two

other employees who were dismissed from service were reinstated. Under what

circumstances they were dismissed and subsequently reinstated is nowhere

mentioned. Demand raised by the respondent for raising an industrial dispute was

ex facie bad and incompetent.'

12. In S.M. Nilajkar v. Telecom District Manager5 the position was reiterated as

follows: (SCC pp.39-40, para 17)

'17. It was submitted on behalf of the respondent that on account of delay in

raising the dispute by the appellants the High Court was justified in denying

relief to the appellants. We cannot agree. It is true, as held in Shalimar Works

Ltd. v. Workmen6 that merely because the Industrial Disputes Act does not

provide for a limitation for raising the dispute, it does not mean that the

dispute can be raised at any time and without regard to the delay and reasons

therefor. There is no limitation prescribed for reference of disputes to an

Industrial Tribunal; even so it is only reasonable that the disputes should be

referred as soon as possible after they have arisen and after conciliation

proceedings have failed, particularly so when disputes relate to discharge of

workmen wholesale. A delay of 4 years in raising the dispute after even re-

employment of the most of the old workmen was held to be fatal in Shalimar Works

Ltd. v. Workmen6. In Nedungadi Bank Ltd. v. K.P. Madhavankutty4 a delay of 7

years was held to be fatal and disentitled the workmen to any relief. In Ratan

Chandra Sammanta v. Union of India7 it was held that a casual labourer

retrenched by the employer deprives himself of remedy available in law by delay

itself; lapse of time results in losing the remedy and the right as well. The

delay would certainly be fatal if it has resulted in material evidence relevant

to adjudication being lost and rendered not available. However, we do not think

that the delay in the case at hand has been so culpable as to disentitle the

appellants to any relief. Although the High Court has opined that there was a

delay of 7 to 9 years in raising the dispute before the Tribunal but we find the

High Court factually not correct. The employment of the appellants was

terminated sometime in 1985-1986 or 1986-1987. Pursuant to the judgment in Daily

Rated Casual Labour v. Union of India8 the Department was formulating a scheme

to accommodate casual labourers and the appellants were justified in awaiting

the outcome thereof. On 16-1-1990 they were refused to be accommodated in the

Scheme. On 28-12-1990 they initiated the proceedings under the Industrial

Disputes Act followed by conciliation proceedings and then the dispute was

referred to the Industrial Tribunal-cum-Labour Court. We do not think that the

appellants deserve to be non-suited on the ground of delay.' "

The above position was highlighted recently in Sudamdih Colliery of Bharat

Coking Coal Ltd. v. Workmen9, SCC pp.334-36, paras 10-12 and Chief Engineer,

Ranjit Sagar Dam v. Sham Lal10."

11.The second argument that the orders of appointment had incorporated the

clause for transfer also does not stand to reason in the light of the judgment

of the Supreme Court in Western India Match Co. Ltd. v. Workmen reported in

(1974) 3 SCC 330. The Supreme Court has held that the terms of appointment

cannot be used to take away the clause in the certified Standing Order. The

relevant passage found in paragraph 10 of the said judgment may be reproduced

below:

"10.In the sunny days of the market economy theory people sincerely believed

that the economic law of demand and supply in the labour market would settle a

mutually beneficial bargain between the employer and the workman. Such a

bargain, they took it for granted, would secure fair terms and conditions of

employment to the workman. This law they venerated as natural law. They had an

abiding faith in the verity of this law. But the experience of the working of

this law over a long period has belied their faith. Later generations discovered

that the workman did not possess adequate bargaining strength to secure fair

terms and conditions of service. When the workmen also made this discovery, they

organised, themselves in trade unions and insisted on collective bargaining with

the employer. The advent of trade unions and collective bargaining created new

problems of maintaining industrial peace and production for the society. It was

therefore considered that the society has also an interest in the settlement of

the terms of employment of industrial labour. While formerly there were two

parties at the negotiating table - the employer and the workman, it is now

thought that there should also be present a third party, the State, as

representing the interest of the society. The Act gives effect to this new

thinking. By Section 4 the Officer certifying the Standing Order is directed to

adjudicate upon "the fairness or reasonableness" of the provisions of the

Standing Order. The Certifying Officer is the statutory representative of the

society. It seems to us that while adjudging the fairness or reasonableness of

any Standing Order, the Certifying Officer should consider and weigh the social

interest in the claims of the employer and the social interest in the demands of

the workmen. Section 10 provides the mode of modifying the Standing Orders The

employer or the workman may apply to the Certifying Officer in the prescribed

manner for the modification of the Standing Orders Section 13(2) provides that

an employer who does any act in contravention of the Standing Order shall be

punishable with fine which may extend to one hundred rupees. It also provides

for the imposition of a further fine in the case of a continuing offence. The

fine may extend to twenty-five rupees for every day after the first during which

the offence continues."

12.As correctly contended by the learned counsel for the petitioners in

the present cases, the Standing Order does not contemplate any such power for

transfer. It is also contended by the workmen that an action of the employer

amounts to an unfair labour practice listing out in V Schedule which is

prohibited by Section 25T of the Industrial Disputes Act. These are all matters

arising out of merits of the case and will have to be adjudicated by the

competent tribunal. Hence this court is not inclined to render any finding on

this score. It is suffice to state that the Government in the guise of

exercising its power under Section 10(1) of the ID Act cannot reach out a

conclusion on merits.

13.In this context, it is necessary to refer to the judgment of the

Supreme Court in Ram Avtar Sharma v. State of Haryana reported in (1985) 3 SCC

189. The following passage found in paragraph 7 of the said judgment may be

usefully extracted below:

"7.Now if the Government performs an administrative act while either making or

refusing to make a reference under Section 10(1), it cannot delve into the

merits of the dispute and take upon itself the determination of lis. That would

certainly be in excess of the power conferred by Section 10. Section 10 requires

the appropriate Government to be satisfied that an industrial dispute exists or

is apprehended. This may permit the appropriate Government to determine prima

facie whether an industrial dispute exists or the claim is frivolous or bogus or

put forth for extraneous and irrelevant reasons not for justice or industrial

peace and harmony. Every administrative determination must be based on grounds

relevant and germane to the exercise of power. If the administrative

determination is based on the irrelevant, extraneous or grounds not germane to

the exercise of power it is liable to be questioned in exercise of the power of

judicial review. In State of Bombay v.K.P. Krishnan4 it was held that a writ of

mandamus would lie against the Government if the order passed by it under

Section 10(1) is based or induced by reasons as given by the Government are

extraneous, irrelevant and not germane to the determination. In such a situation

the Court would be justified in issuing a writ of mandamus even in respect of an

administrative order. Maybe, the Court may not issue writ of mandamus, directing

the Government to make a reference but the Court can after examining the reasons

given by the appropriate Government for refusing to make a reference come to a

conclusion that they are irrelevant, extraneous or not germane to the

determination and then can direct the Government to reconsider the matter. This

legal position appears to be beyond the pale of controversy."

14.Therefore, the Government of India's refusing to refer the three cases

of the workmen for adjudication is clearly erroneous and liable to be interfered

with by this court. The petitioner union is entitled to succeed. Hence the

impugned orders stand set aside. A direction is issued to the first respondent

to refer the cases of the three workmen for adjudication by the Central

Government Industrial Tribunal at Chennai. This exercise shall be undertaken

within a period of two months from the date of receipt of copy of this order,

without fail.

15.Accordingly, all the three writ petitions will stand allowed. However,

there will be no order as to costs. Consequently, connected miscellaneous

petitions stand closed.

vvk

To

1.The Secretary to Government,

Ministry of Labour,

Government of India,

New Delhi.

2.The Assistant Commissioner of Labour (Central),

Lady Doak College Road,

Chinna Chokkikulam,

Madurai-625 002.

3.The Management,

The India Cements Ltd.,

Sankar Nagar,

Tirunelveli District.

No comments: